Sidewalks


The Longmeadow Public Works Department has contracted D. & P.  Morais Construction to install a new sidewalk on the following streets:

Cooley DriveRosemore Street
Longmeadow Street (across from Bark Haul Rd)Lawrence Drive
Shaker Road (From Hazardville to Maple)South Park Avenue
Coventry Lane- To begin work on 7/17


The work is scheduled to begin May 15th, 2023. Project completion is expected to be before July 1st, 2023 .  South Park Avenue will be the first street to be worked on.

Lawn Sprinklers: In an effort to reduce damages to lawn irrigation systems, please mark irrigation lines and sprinkler heads as well as invisible dog fences located at the edge of the roadway. Flags to mark irrigation lines/heads and underground fences are available at the Department of Public Works. Should there be any damage to the marked irrigation or fence, the Town’s contractor will make the necessary repairs. The contractor will make every effort to avoid your irrigation systems. Damage to unmarked systems will not be repaired by the Town.

Following sidewalk installation, D. & P. Morais Construction Company will be placing screened topsoil and grass seed in disturbed areas. We ask that you assist with the process by providing water and additional grass seed (as deemed necessary) in order to accomplish successful lawn restorations.

In an effort to facilitate weekly refuse collection, residents are asked to have their refuse and recycling curbside by 7:00 a.m., especially during periods construction work is taking place on your street.

We will make every effort to notify residents of any substantial schedule changes.  Please check the Town Facebook page (facebook.com/LongmeadowMA) for current updates. Please report any problems or concerns by contacting the Engineering Department at (413) 567-3400 or email publicworks@longmeadow.org. 

Respectfully,

Longmeadow Engineering Department

 

Longmeadow Sidewalk Plans for 2023