Storm Drainage Work

The Longmeadow Public Works Department has contracted with Mass-West Construction to preform stormwater improvement upgrades on Shady Knoll Drive.

The outfall project consists of improvements including but not limited to, installation of manhole, installation of reinforced concrete pipe, installation of flared end outfall, installation of gravel fill, and installation of rip rap. Roadway improvements including but not limited to, the disposal of bituminous concrete pavement; installation of new catch basins, installation of new catch basin frames and covers, placement of hot mix asphalt, removal and installation of new bituminous concrete berm, and installation of road markings.

Work is to begin 7/11/2023.

Substantial Completion for this project will be by September 1,2023.


Shady Knoll Outfall Improvement Plans